Exchange of primary components on a gas turbine with 45 MW of installed power and upgrade the subsequent gas fired exhaust heat steam generator for supplying the chemical park GENDORF. The planning, implementation, and commissioning phases of the plant under the scope of the "Power Plant Modernization" project family presented a special challenge. Close consultation with parallel new construction projects and maintaining the secure and reliable power plant operations needed to be taken into account, along with the short completion time frame of 12 months.