General planning (EPCM) re-cooling plant

A re-cooling plant with approximately 200 MW of cooling power was installed with two cooling circuits for a polyolefin market leader in southern Germany. In addition, a cooling water distribution network was erected and the cooling water treatment plant was installed. A special challenge was presented by the fast-track implementation in parallel to erecting a polyolefin production plant and the concurrent expansion of a large production plant.